Just a quick question . When fitting the bathroom sink.Do you fit the sink and then run the tiles up,or tile then fit the sink over the tiles .
Discuss fitting a bathroom sink in the Canada Tile Advice area at TilersForums.com.
Not sure if this is true or just hearsay but a couple of the electrical subbies I use have said that IF your electrical system is fully protected with RCDs (ie. all circuits in your consumer unit flow from RCDs) there is no longer a requirement for earth bonding of metalwork within that building. I think you'll need to read the building regs to check if that's actually true. However, if any of your circuits are not RCD-protected, you should bond all exposed metalwork in wet areas to earth. That means, pipework in copper, steel or lead, cast iron or steel baths, even radiators and towel rails - basically anything metal that could be touched.