ChiversTiling

Hi all pros

Had a look at a job that is 28m2 patio laying 600x600 Porcelain that will need SLC as concrete looks uneven in places going by the look of it as didn't have my levels on me at the time

The weather an't all that atm only time I could start it be in a months time but by then the frost will start kicking in, would ya gamble on hoping the weather will hold of or waiting till summer comes?
 
C

ChiversTiling

Bought a draper Gazebo the other day as was fed up of my tools getting wet when knocking up gear outside but not enough to cover that sort of area, have to go down on my waiting list
Cheers peeps
 

Rich Midge

TF
Esteemed
Reaction score
396
Points
598
Location
Liverpool
I layed 30 to 40 metres on the entrance ramp to my brother's hotel in January. It's on the seafront and open to the elements. Wasn't keen to do it but it's the only time the hotel is closed. Even posted a thread on here about it. Spoke with TileMaster at the time and used Ultimate (solid bed, back buttered, obviously) and Grout 3000 and covered it each night. I realise it's not been down a year yet but it looks no different now than it did after its final wash down. I'd always advise the client to wait but sometimes it's not possible.
 

Dan

Admin
Staff member
Reaction score
5,031
Points
1,318
Location
Staffordshire, UK
I guess you can tile it now, and if you're worried about patchy grout, grout it at a later date perhaps?
 

widler

TF
Esteemed
Arms
Reaction score
2,341
Points
1,328
Location
England
Its one of them, ive done loads of rendering in the rain ect , just put a big tarpolin over the scaffold and roof, more or less same risks as tiling or flagging outside , up to you if yiu want to risk it, its easy enough to cover , but yiu would have to cost it in with the price
 
A

antded

Just finished the Victorian path, as per previous post. Tiled in 3 days, but took nearly a fortnight with prep, rained off days etc. Temperatures were very mild for time of year with night temps no lower than 5degC. In my humble opinion, wait for the Spring...... oh and make sure you choose a suitable exterior levelling compound ha ha.
I would use Tilemaster Ultimate, excellent product
 
D

Dougs Third Go

my main concern would be frost, both in the air and rising up from the ground, don't know any manufacturers that'll guarantee their adhesive below +5deg C
 

Reply to Is It A Good Time To Start Doing Exterior Tiling in the Australia Tiling Forum area at TilersForums.com

There are similar tiling threads here

Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
767
I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe...
Replies
1
Views
605
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
556
The trustpilot reviews for tilers-world are excellent, but there's not a huge number of them...
Replies
3
Views
914
Hi all! Just wondering what the best advice is for book-keeping? Been self employed now for a...
Replies
1
Views
562

Advertisement

New Tiling Questions

Replies you've not seen

Top