Does anybody how long s and c screed has to down before ufh can be commissioned or is it moisture dependent.
 
O

Old Mod

Although there may be still moisture present, I think Portland cement takes 21-28 days to cure.
I’m fairly confident you need to wait 21 days.
Hopefully someone else can confirm, or not as the case may be.
 

Uheat - Jake

TF
TF Official Sponsor
Reaction score
143
The general rule we've always been told is 1 day per 1mm of screed, but as the system is used for the first time, the mixing valve must be set to the minimum setting to let the moisture in the
screed to dry out. The temperature should be increased by 2 degrees every day until the mixing valve is set at 45°C.
 
O

Old Mod

The general rule we've always been told is 1 day per 1mm of screed, but as the system is used for the first time, the mixing valve must be set to the minimum setting to let the moisture in the
screed to dry out. The temperature should be increased by 2 degrees every day until the mixing valve is set at 45°C.
Yes that’s correct 1mm per day to 40mm,
1mm per 2 days over that, are the standard drying times for a s/c screed
And 2 degrees a day increase in temp from min is what we advise, but quite often ufh is used to speed things along a little.
My understanding is that you must wait a minimum of 21 days before the ufh can be turned on for this process.
Jerry is looking for confirmation on that.
Are you able to help with that @Uheat - Jake please?
 

Uheat - Jake

TF
TF Official Sponsor
Reaction score
143
Yes that’s correct 1mm per day to 40mm,
1mm per 2 days over that, are the standard drying times for a s/c screed
And 2 degrees a day increase in temp from min is what we advise, but quite often ufh is used to speed things along a little.
My understanding is that you must wait a minimum of 21 days before the ufh can be turned on for this process.
Jerry is looking for confirmation on that.
Are you able to help with that @Uheat - Jake please?
From my understanding it's at the end of the screed curing process as if you input any heat into it before its cured it can cause cracks in the screed.
 
H

hmtiling

From my understanding it's at the end of the screed curing process as if you input any heat into it before its cured it can cause cracks in the screed.
It's my understanding that screed drying and curing are different things completely. I've always thought heating of traditional screeds can be commissioned after 28 days lowest setting up 2 degrees a day as above. A 70mm screed with ufh would be 100 days before heating can go on otherwise
 

Ajax123

TF
Esteemed
Arms
Reaction score
934
Cement Based screed should not be commissioned before 21 days from curing but should be cured for 7 days after installation under polythene so if done correctly would be 28 days

Anhydrite screed UFH can be commissioned after 7 days

the process is always a debate as different standards suggest different methods however my advice is treat them both the same

switch on after above periods of time at minimum manifold temperature. usually 35 degrees C and leave for 3 days. then increase by 5 derees per day up to a maximum of 55 degrees and leave at this for 3 days. then reverse the process.

To commission the heating properly the flow temperature should not be limited by room stats i.e. make sure the stats are disconnected ad operate the temperatures manually via the manifold mixing valve or at the boiler.
 
O

Old Mod

.

To commission the heating properly the flow temperature should not be limited by room stats i.e. make sure the stats are disconnected ad operate the temperatures manually via the manifold mixing valve or at the boiler.

Thanks Alan.
 
D

Dumbo

Cement Based screed should not be commissioned before 21 days from curing but should be cured for 7 days after installation under polythene so if done correctly would be 28 days

Anhydrite screed UFH can be commissioned after 7 days

the process is always a debate as different standards suggest different methods however my advice is treat them both the same

switch on after above periods of time at minimum manifold temperature. usually 35 degrees C and leave for 3 days. then increase by 5 derees per day up to a maximum of 55 degrees and leave at this for 3 days. then reverse the process.

To commission the heating properly the flow temperature should not be limited by room stats i.e. make sure the stats are disconnected ad operate the temperatures manually via the manifold mixing valve or at the boiler.
Thanks
Much appreciated
 

Jimcub

TF
Reaction score
1
As a diyer who put his own UFH in I can vouch for the above with a cement based screen. I used some lads from Bolton who laid 33sq mts for me with a laser and it was within 1mm according to the tiler.

Let it dry and cure slowly I waited till after the 21 days, then from a low heat did increase it 2 deg each day then had the tiles put down when it was cold. Keep the pressure in the pipes whilst cold I was told and did just that.
Result is a flat warm conservatory 21 deg all winter, heat loss was minimal and it was kept on 24/7. Not seen a great deal of difference in gas use as we didn't have to use the central heating as the UFH warmed the already warm house.
 

Reply to How long before ufh can be commisioned in the Tiling on Underfloor Heating area at TilersForums.com

Or checkout our tile courses and training forum or the Tile Blog / Latest Blog Posts

There are similar tiling threads here

    • Like
Bathroom floor. I would be grateful for advice on how to prepare my bathroom sub floor ready for...
Replies
1
Views
353
I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe...
Replies
1
Views
543
Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
681
10 Tiling Tips for Fixing Tiles to Bathroom Walls = From UKTilingForum.co.uk There are a few...
Replies
1
Views
565
The trustpilot reviews for tilers-world are excellent, but there's not a huge number of them...
Replies
3
Views
885
This website is hosted and managed by www.untoldmedia.co.uk. Creating content since 2001.
Tile Contractor Forum. The useful tile contractor website.

Replies you've not seen

New Tiling Questions

UK Tiling Forum Stats

Threads
67,343
Messages
881,166
Members
9,535
Latest member
Teejay
Top