Imagine you purchase a house that is totally neglected and been empty for years. Roof leaking, ceilings falling down, no central heating etc... total mess.
After completely gutting and stripping it back to a shell - what would be the order to do things (tradewise)?
 
D

david campbell

roof
windows/door
roughed out(plumbers joiners sparks etc)
finishings(painters,finishing joiner,tiler)
 
W

White Room

Roof
First fixing of electric and plumbing/heating/carpentry, door frames
Plasterboard ceiling
Plastering/dry linning
Kitchen/bath etc
Tiling
Second fixings, skirts, sockets etc
Decorating
Think thats about it
 

Reply to Full on house refurb in the UK Tiling Forum area at TilersForums.com

There are similar tiling threads here

I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe...
Replies
1
Views
644
Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
845
Hi all! Just wondering what the best advice is for book-keeping? Been self employed now for a...
Replies
1
Views
594
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
600
Hi all. Just wanting some advice and wondering what the pros in here are using nowadays for...
Replies
2
Views
577
Please visit our sponsor websites, they keep the forum free to use!

Advertisement

New Tiling Questions

Replies you've not seen

Top