Bad job or unavoidable?

Discuss Bad job or unavoidable? in the America Tile Forum area at TilersForums.com.

Hi,

Currently getting a new bathroom fitted with metro tiles. The tiler is back today to finish off grouting and laying the floor tiles. I've gone in this morning to check the last 2 days work (having been busy working myself so couldn't check before now) and I am pretty unhappy with the way the tiles have been laid very unevenly in my opinion. Is this acceptable or unavoidable for some reason? Thanks.
 
20210711_063012.jpg
 

Dave

TF
Staff member
Arms
Esteemed
Subscribed
389,894
1,000,000
Co.Durham
Just spoke to the guy and this is what he said. Unfortunately didn't let me know otherwise I would have got it replastered. It is an old, terraced, edwardian house so doesn't help either!
Plastering it wouldn’t have helped, would need dry lining as too much to make up with skim.
 
Two things you need to do:

1 . Hold a (decent length) level (vertically) against the vertical edge of one tile to show how aligned the vertical edges of the tiles are.

2. Hold a (decent length) level vertically against the corners of your walls and photograph the bubble to show how plumb your walls are.

It's hard to tell from the photos you posted, but it does look to me like the tiles are not vertically aligned (I held a straight edge rule on one tile edge and the tiles are out of plumb on all your photos so it's suspicious).... However, it could be a combination of both as tiles are way out looking at your photos.


If your walls really are that far out, that should have been mentioned to you (if the tradesman was any good) before the job was started so you were aware of the problem --- it could have been easily rectified by overboarding. Another potential issue is that if your walls are that far out, a lot of not-very-good tilers will start tiling from one corner of the room relying on the corner edge as their plumb line. Problem is, if that's out (and it usually is) the tiles will never be properly vertically aligned - that might have been done in your case as you've not photographed all corners.
 
Last edited:

Kevbos

Arms
35
443
London, UK
Two things you need to do:

1 . Hold a (decent length) level (vertically) against the vertical edge of one tile to show how aligned the vertical edges of the tiles are.

2. Hold a (decent length) level vertically against the corners of your walls and photograph the bubble to show how plumb your walls are.

It's hard to tell from the photos you posted, but it does look to me like the tiles are not vertically aligned (I held a straight edge rule on one tile edge and the tiles are out of plumb on all your photos so it's suspicious).... However, it could be a combination of both as tiles are way out looking at your photos.


If your walls really are that far out, that should have been mentioned to you (if the tradesman was any good) before the job was started so you were aware of the problem --- it could have been easily rectified by overboarding. Another potential issue is that if your walls are that far out, a lot of not-very-good tilers will start tiling from one corner of the room relying on the corner edge as their plumb line. Problem is, if that's out (and it usually is) the tiles will never be properly vertically aligned - that might have been done in your case as you've not photographed all corners.
To me it looks like !what happens all too often , a plumber has also been involved in the new bathroom , as capped pipes in picture , it's very easy for criticism, but we don't know budgets etc etc !! Is a builder involved , it's not right that walls are wrong , but who was responsible for preparation??
 
To me it looks like !what happens all too often , a plumber has also been involved in the new bathroom , as capped pipes in picture , it's very easy for criticism, but we don't know budgets etc etc !! Is a builder involved , it's not right that walls are wrong , but who was responsible for preparation??
Doesn't detract from the fact that whoever tiled it didn't do a good job. If the plumber left capped pipes to tile around then that's fine and in ideal world, just what you want..... The tiler should have checked the room for plumb before doing anything, in this case as the walls are waaaay off plumb he should have let the client know before just going ahead and starting the job...... I mean, that's what is meant by professionalism.
 

Kevbos

Arms
35
443
London, UK
Doesn't detract from the fact that whoever tiled it didn't do a good job. If the plumber left capped pipes to tile around then that's fine and in ideal world, just what you want..... The tiler should have checked the room for plumb before doing anything, in this case as the walls are waaaay off plumb he should have let the client know before just going ahead and starting the job...... I mean, that's what is meant by professionalism.
A professional plumber would have also brought this up as usually its there job as s whole
 

Kevbos

Arms
35
443
London, UK
A professional plumber would have also brought this up as usually its there job as s whole
And what I mean is , do we know if there is a builder , or plumber etc who's job it is ? Do we know the circumstances of the tiler doing the job , because if it is someone else's job , the tiler may have been told to just tile it , ideal world situations are great if they work , but if you book in 2 or 3 days to do a job !turn up , walls are not great ,then told to do best you can ! Which does happen , a situation arises , you go home have 3 days off , or raise problem with the builder or plumber etc , if they are not willing to rectify walls , what do you do ?? Go to customer who essentially not your customer and raise issue !! Lose all future work with builder plumber or do as you are told ?? Unfortunately there are to many poor trades out there
 

Reply to Bad job or unavoidable? in the America Tile Forum area at TilersForums.com

There are similar tiling threads here

    • Like
  • Article
Morning all. Dan asked me to post up a thread about our training centre which he can then use for feedback. We have been established in Newport, South Wales (just across the bridge from Bristol)...
Replies
6
Views
1K
Hi, I'm new to the forum and fairly new to tiling, my only previous "proper" job was my recent bathroom (600x600 porcelain, about 25m walls and floors) which went pretty well. I'm now having a go...
Replies
3
Views
2K
Posting a tiling question to the forum? Post in Tilers' Talk if you are unsure which forum to post in. We'll move it if there's a more suitable forum.