Blunt Tool

It'll be a dry mix wetted!
It was Mandarin Stone I laid, hammered finish limestone, 5mm joints laid into 24:1 sharp sand and cement, semi dry with SBR slurry done in stretches. The grout was hand made soft washed sand, snowcrete and yellow colouring. I sprinkled water into the joints then soft brushed the dry mix into joints, then compacted with trowel. The mix pulls the water up then after a time pointed and brushed away excess.
 
B

Blunt Tool

Stone supplier has recommended fitting their 20mm (900x600) stone outside on a 50mm sand/cement bed over hardcore. Sbr slurry on the back to reduce staining.
Anyone believe this is a correct method of installation or what are your alternatives.
Your thoughts please.
Forgot to say regards the hardcore, I got the contractors to roll it tight, then put in a 1 inch bed of sharp sand raked and rolled tight then dampened and used building paper!
 
J

J Sid

It was Mandarin Stone I laid, hammered finish limestone, 5mm joints laid into 24:1 sharp sand and cement, semi dry with SBR slurry done in stretches. The grout was hand made soft washed sand, snowcrete and yellow colouring. I sprinkled water into the joints then soft brushed the dry mix into joints, then compacted with trowel. The mix pulls the water up then after a time pointed and brushed away excess.
I would do a much stronger mix for the sand and cement 10 or 8 : 1
 
J

J Sid

that was the mix we used years back for warehouse floors mainly, taking heavy traffic.
but surely how well the mix was bedded / compressed when fitting the tile / stone has a big influence on how strong or brittle the cured sand and cement mix will be.
 
B

Blunt Tool

Served half my time with pile of sharp sand, bags of cement, mixing board, barrel of water and a shovel for Toffolo Jackson. Don't know how many tons per day me and another apprentice mixed and carried. But tradesmen were scary guys back in that days and if they said 24 shovels to 1 bag cement guess what we mixed? Stuck with me all my life and never mess with it and never let me down :)
 

Reply to 20mm stone paviours outside. in the Specialist Tile -Stone, Porcelain, Glass area at TilersForums.com

There are similar tiling threads here

Good morning all. After a little advice. I'll post pictures a bit later. However.... The...
Replies
6
Views
908
I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe...
Replies
1
Views
667
Hi all! Just wondering what the best advice is for book-keeping? Been self employed now for a...
Replies
1
Views
631
    • Like
A little help guys. I've been asked to price 71sqm of limestone flooring. My issue is this...
Replies
2
Views
237
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
644
Posting a tiling question to the forum? Post in Tilers' Talk if you are unsure which forum to post in. We'll move it if there's a more suitable forum.
Please visit our sponsor websites, they keep the forum free to use!

Advertisement

New Tiling Questions

Replies you've not seen

Top