Just one issue I can see here, 5 days before the tiler starts, that's not going to be long enough to get the install done and commission the floor before the tiling starts. Disaster in the making IMO.
 

Dan

Admin
Staff member
Reaction score
5,032
Oh ye. Never thought of that. Perhaps upto the customer once being advised though to arrange with the tiler a suitable time?
 