Hi, got a job coming up next week of tile on a rapid set concrete floor with a pipe based under floor heating system fitted. Large format 600 x 900 x 20 natural stone tiles are being laid on top. Been told by the builder the concrete is being laid on the piping this Friday and I should be able to tile on it the following Monday. This seems too soon to me, especially in this colder weather. It's in a new extension and totals approx 80m squared. No heating till the UFH can be fired up. I'm worried about possible shrinkage problems if I tile on it too soon. Also not sure about possibility of decoupling / using ditra mat over a heating system.

Advice required about how long before starting tile and should I advise builder they should put a large de humidifier in the room, cheers.
 

Ajax123

TF
Arms
Reaction score
933
Sounds like a nightmare in waiting...
 
OP
J

J Sid

you need full spec on the concrete being put down, may need the surface sanding. As said, the ufh needs commissioning, and yes Ditra.
 
OP
F

Flintstone

Lots of potential issues here. Need more details on the screed, but whichever screed it is it shouldn't be tiled on until the heating has been commissioned properly.
 
OP
W

wayfoward

Thanks for your replies, a nightmare in waiting is exactly what I want to avoid being associated with. Forgot to mention that, being an extension, half the floor was old concrete (insulation issues?) and half the actual extension when I looked in 2 weeks ago. I see major issues with the floor heating crossing the two. I don't know if its the builder or a specialist who's installing the pipework.
Will advise the builder to zone floor in 2 halves if possible so floor heating is even. I should point out I just tile and know nothing about how building / heating system should be done. Just googled commissioning UFH for an idea of what's done. Came up with this:

Underfloor Heating and Screeding | The RIBA Zone | Flowcrete UK - http://www.flowcrete.co.uk/campaigns/flowcrete-and-riba/underfloor-heating-and-screeding/

Will also advise builder floor needs to be commissioned before I start tile. Builder / customer won't like that, as I'm basically telling him / them I won't start tile to the new year. I'm thinking ditra mat for sure now, bearing in mind all the above. Going to stop by the job this morning for a chat as I'd like to think the builder would like to avoid a nightmare in waiting too.
 

Reply to Drying time for rapid set concrete please in the Specialist Tile -Stone, Porcelain, Glass area at TilersForums.com

Or checkout our tile training advice or the Tile Standards

This website is hosted and managed by www.untoldmedia.co.uk. Creating content since 2001.
Please visit our sponsor websites, they keep the forum free to use!

New Tiling Questions

UK Tiling Forum Stats

Threads
66,600
Messages
866,704
Members
9,511
Latest member
mmcdon47
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock