Welcome to Tilers Forums Tiling Forum
The UK's Biggest Tiling Forum for DIY and Professional Tilers; find
- » Tile Advice for Bathroom Tiles, Kitchen Tiles, Wall Tiles, Floor Tiles
- » Customers can Find a Tiler, or Wall and Floor Tilers can Find Customers
- » Tiling Tools, Tile Adhesive, Tile Grout and other Tile Products
- » Advice and Discussion related to Tiling Courses and Tiling NVQ's
- » Professional Tilers can find Business Advice, Discounts, Trade Accounts
DIY and Professional Wall and Floor Tilers are Welcome
Advice from by Tilers, Manufacturers, Distributors and Tile Suppliers
REGISTER HERE FOR FREE
p.s.: Registered members will not see this ad
Discuss
Tiling & electric UFH onto new screed in the
Tiling Forum at TilersForums;
A 60-70mm deep standard sand/cement screed has just been laid in my new kitchen, sitting on 80mm insulation boards on top of a new concrete slab (laid 6 weeks ago). ... -
New TilersForums Contributor
Tiling & electric UFH onto new screed
A 60-70mm deep standard sand/cement screed has just been laid in my new kitchen, sitting on 80mm insulation boards on top of a new concrete slab (laid 6 weeks ago). On the new screed I plan to lay (as soon as possible !) :
1) 10.5mm Econoboard foam insulation boards (stuck down with a suitable adhesive)
2) Thermonet electric UFH matting
3) Flexible latex
4) 600x600mm ceramic tiles (using flexible SPF tile adhesive)
I'm getting conflicting advice over how long I need to wait for the screed to dry before starting the UFH & tiling. My tile shop says "4 to 6 weeks", my builder says "a couple of days should be fine". I suspect the answer lies somewhere in the middle.
I've looked at other threads in this forum that mention "Ditra matting" and "BAL Green adhesive" as ways of shortening the wait, but have a couple of further questions :
1) Will my 10.5mm layer of Econoboard insulation boards achieve essentially the same thing that the Ditra matting is for, presumably being to separate the tiles from the screed so any slight shrinkage on drying doesn't disturb the tiles above ?
2) If the answer to this is Yes, what is the earliest I can go ahead and start to stick down the Econoboards on the new screed ? The room is well ventilated and, given the British summer, the temperature is typically around 20 deg C. If I wait a week, is that sufficient ?
3) Would I be wise to use BAL Green adhesive to stick down the Econoboards to the new screed ? Or is there something else I should use ?
All advice gratefully received !
-
-
Re: Tiling & electric UFH onto new screed
http://www.thermonet-online.co.uk/im...Econoboard.pdf
i had a look through this and the only thing i could see was point 1
-make sure the surface is ready for tiling,this i would assume is waiting the neccesary time you could tile onto the surface which is 1mm per day drying time so about 6 weeks is a lot closer thn your builders advice!
i'm not sure how it works with using green screed or similar products and i would suggest phoning or e-mailing there technical dept
ps welcome to the forum
alcohol-the cause and solution to all of lifes problems http://absolute-tiling.webs.com/ tiler in east kilbride/tiler in glasgow/tiler in hamilton Tiler in east kilbride-AbsoluteTiling
-
-
Re: Tiling & electric UFH onto new screed
imo i,would give it at least 4 weeks, before attempting to stick the boards on to the screed,
-
-
Re: Tiling & electric UFH onto new screed
Screed needs to be at least 3 weeks old (British Standard for tiling) but domestically should be a minimum of 65mm if it is a floating screed (which yours is)
stick your foam boards down with Mapei Keraquick
Secure your heating mat and blind with Mapei Fibreplan
Commission underfloor heating by bringing temperature up to intended working temp. at 5C per day and run for three days then switch off and cool for 24 hours.
Fix your large format ceramic in Keraquick
Grout minimum 3mm joints with Ultracolor Plus
Allow 21 days to dry out following completion of grouting and movement joints
Switch on heating as per commissioning process
The above follows British Standard and National Builduing Specification recommendations
-
The Following User Says Thank You to dock For This Useful Post:
-
Re: Tiling & electric UFH onto new screed
"a couple of days should be fine" - Shocking coming from a "builder"!
-
-
Re: Tiling & electric UFH onto new screed
Using Bal Green Screed should allow you to tile a concrete screed a week after laying it, however, you wont be able to turn on the UFH for the full 6 week period to fully allow the screed to properly dry out. This is what BAL technical dept told me a couple of months ago anyway! If you use Mapei Keraquick, you should wait three weeks from screed being laid to start fixing the boards etc as per Dock's post above
And 
Chris
Last edited by chris.tiling; 08-06-2010 at 03:02 PM.
Tiler in Poole,
Tiler in Bournemouth,
Tiler in Ferndown,
Tiler In West Moors,
Tiler in Wimborne,
Tiler in Blandford,
Tiler in Wareham,
Tiler in Swanage,
Tiler in Christchurch,
Tiler in Ringwood,
Tiler in Bere Regis.
www.christiling.co.uk
-
Similar Threads
-
By wilfredolimb in forum Electric Underfloor Heating
Replies: 5
Last Post: 03-12-2009, 11:43 AM
-
By Don in forum Electric Underfloor Heating
Replies: 3
Last Post: 14-01-2009, 11:09 PM
-
By wayneski in forum Tiling Forum
Replies: 10
Last Post: 31-10-2008, 01:33 PM
-
By Tilers, Tiling & Tiles in forum RSS Feeds
Replies: 0
Last Post: 20-10-2008, 01:31 AM
-
By Dan in forum Tiling Courses Feedback
Replies: 0
Last Post: 02-04-2006, 10:49 PM
Visitors found this page by searching for:
electric ufh over cement screed
,
tiling on standard cement screed
,
how long to wait screed ufh
,
how long for screed to dry before laying tiles
,
does econoboards need fixing down
,
can you lay ceramic tiles on wet concrete screed
Tags for this Thread
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules
Tilers Forums is the UK's largest wall and floor
tiling forum. Advice is provided free of charge to all users. Tilers Forums does not take responsibility for any loss or damage caused due to following advice found on this forum. All wall and floor tiling should be carried out by a qualified wall and floor tiler. Views expressed on this forum are of the users and not
Tilers Forums. Views expressed on this tiling forum are of the contributor only and not the forum as a whole. Not all views should be taken as fact but simply the opinion of the person posting. Readers are reminded to seek professional advice before undertaking any wall and floor tiling project.
Tilers Forums is a Trading Style of Untold Developments Ltd.
Search Engine Optimisation, Web Development and Online Marketing for the UK.
Bookmarks