Welcome to Tilers Forums Tiling Forum


The UK's Biggest Tiling Forum for DIY and Professional Tilers; find


  •  » Tile Advice for Bathroom Tiles, Kitchen Tiles, Wall Tiles, Floor Tiles
  •  » Customers can Find a Tiler, or Wall and Floor Tilers can Find Customers
  •  » Tiling Tools, Tile Adhesive, Tile Grout and other Tile Products
  •  » Advice and Discussion related to Tiling Courses and Tiling NVQ's
  •  » Professional Tilers can find Business Advice, Discounts, Trade Accounts

DIY and Professional Wall and Floor Tilers are Welcome


Advice from by Tilers, Manufacturers, Distributors and Tile Suppliers


REGISTER HERE FOR FREE


p.s.: Registered members will not see this ad

Results 1 to 5 of 5
Discuss BS 5385:Part 4 - 2 wks before use shower?? in the Tiling Forum at TilersForums; I know that after tiling and grouting a shower BS recommend not using shower for 2 weeks to comply with BS 5385:Part 4:2009, clause 7.2.1.. DOES anyone know why. Adhesive ...
          
  1. #1
    Ray
    Ray is offline
    New TilersForums Contributor Ray's Avatar
    Join Date
    Apr 2009
    Posts
    10
    Thanks
    0
    Thanked 0 Times in 0
    Posts

    Default BS 5385:Part 4 - 2 wks before use shower??

    I know that after tiling and grouting a shower BS recommend not using shower for 2 weeks to comply with BS 5385:Part 4:2009, clause 7.2.1..
    DOES anyone know why. Adhesive is dry and grout is dry (manufacturer recommended times ) usually 24hours +. What takes 2 weeks.?

  2. #2
    Tilers Forums Arms Member
    faithhealer's Avatar
    Join Date
    Apr 2007
    Location
    Sedgefield
    Posts
    8,280
    Thanks
    2,527
    Thanked 2,472 Times in 2,006
    Posts

    Default Re: BS 5385:Part 4 - 2 wks before use shower??

    I'm sure Bal have two weeks in their grouts small print

  3. #3
    Administrator


    Dave's Avatar
    Join Date
    May 2007
    Location
    County Durham
    Posts
    54,472
    Thanks
    9,718
    Thanked 14,141 Times in 9,988
    Posts
    Blog Entries
    1

    Default Re: BS 5385:Part 4 - 2 wks before use shower??

    Quote Originally Posted by Ray View Post
    I know that after tiling and grouting a shower BS recommend not using shower for 2 weeks to comply with BS 5385:Part 4:2009, clause 7.2.1..
    DOES anyone know why. Adhesive is dry and grout is dry (manufacturer recommended times ) usually 24hours +. What takes 2 weeks.?

    Tensile/structural strength..

  4. #4
    TF Moderator & Pro Tiler


    whitebeam's Avatar
    Join Date
    Apr 2007
    Location
    Hertfordshire
    Posts
    22,960
    Thanks
    2,314
    Thanked 4,999 Times in 4,312
    Posts

    Default Re: BS 5385:Part 4 - 2 wks before use shower??

    Cement adhesive may have set but need's the time then to cure to give their full strength, thats why 2-4 weeks
    "Experience is simply the name we give our mistakes"

  5. #5
    Ray
    Ray is offline
    New TilersForums Contributor Ray's Avatar
    Join Date
    Apr 2009
    Posts
    10
    Thanks
    0
    Thanked 0 Times in 0
    Posts

    Default Re: BS 5385:Part 4 - 2 wks before use shower??

    Thanks guys...Now I know why i am telling clients not to use shower for 2 weeks..They are often dissapointed when all is finnished and i say can't use shower.

Similar Threads

  1. questions on shower design and fitting
    By alan beard in forum Tanking & Wetrooms
    Replies: 1
    Last Post: 01-11-2009, 10:16 AM
  2. DIY Related: B & Q Walk in shower
    By stryd in forum Tiling Forum
    Replies: 12
    Last Post: 04-08-2009, 03:18 PM
  3. replacing bath with shower
    By telfian in forum Tanking & Wetrooms
    Replies: 1
    Last Post: 12-07-2009, 08:48 PM
  4. Help!: Leaking shower - and I'm clueless
    By 2runningcats in forum Tiling Forum
    Replies: 10
    Last Post: 09-05-2009, 06:54 PM
  5. Choosing a wet room shower tray
    By Dave in forum Tanking & Wetrooms
    Replies: 1
    Last Post: 07-02-2009, 06:59 PM

Visitors found this page by searching for:

bs5385 part 4

bs 5385 part 4

bs 5385

bs5385-4

bs for tiling 5385bs 5385 – part 4 section 6.3).bs 5385-part 4 section 6.3shower grout 2 weeksbs5385

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Tilers Forums is the UK's largest wall and floor tiling forum. Advice is provided free of charge to all users. Tilers Forums does not take responsibility for any loss or damage caused due to following advice found on this forum. All wall and floor tiling should be carried out by a qualified wall and floor tiler. Views expressed on this forum are of the users and not Tilers Forums. Views expressed on this tiling forum are of the contributor only and not the forum as a whole. Not all views should be taken as fact but simply the opinion of the person posting. Readers are reminded to seek professional advice before undertaking any wall and floor tiling project.

Tilers Forums is a Trading Style of Untold Developments Ltd. Search Engine Optimisation, Web Development and Online Marketing for the UK.
DMCA.com
[Output: 75.43 Kb. compressed to 68.85 Kb. by saving 6.58 Kb. (8.72%)]

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28