Welcome to Tilers Forums Tiling Forum
The UK's Biggest Tiling Forum for DIY and Professional Tilers; find
- » Tile Advice for Bathroom Tiles, Kitchen Tiles, Wall Tiles, Floor Tiles
- » Customers can Find a Tiler, or Wall and Floor Tilers can Find Customers
- » Tiling Tools, Tile Adhesive, Tile Grout and other Tile Products
- » Advice and Discussion related to Tiling Courses and Tiling NVQ's
- » Professional Tilers can find Business Advice, Discounts, Trade Accounts
DIY and Professional Wall and Floor Tilers are Welcome
Advice from by Tilers, Manufacturers, Distributors and Tile Suppliers
REGISTER HERE FOR FREE
p.s.: Registered members will not see this ad
Discuss
Expansion joint / cold joint in the
Tiling Forum at TilersForums;
Finally got some ply down and am nearly ready for screeding.
Been reading up and i think what i may need is what is referred to as a cold joint.
... -
TilersForums Contributor
Expansion joint / cold joint
Finally got some ply down and am nearly ready for screeding.
Been reading up and i think what i may need is what is referred to as a cold joint.
The plan is to put something along the edges of the ply so we can screed upto it and then when this has gone off remove and fill with the same flexible adhesive i will be using for the tiles?
Screed will be 50mm depth, but what do i use to create the gap and what sort of width should it be? Or if i am heading down the wrong route please advise as would like to get the screeding down at the end of the week.
Pics can be found here as i can't seem to be able to get them on here.
kitchen
-
-
Re: Expansion joint / cold joint
-
-
TilersForums Contributor
Re: Expansion joint / cold joint
cheers Dave, if i am struggling with pics........
-
-
Re: Expansion joint / cold joint
Not sure I understand what this is getting at. Why do you need a "cold joint".
Also what type of screed are you using as standard sand cement screed will not accept a great deal of deflection without cracking. On these type of old solid timber joists you need to be a bit carefull about this bit because you don't want the screed to crack. I would also put a polythene slip membrane under the screed on top of the ply first. This helps to prevent restraint and allows the screed to move "independently" of the ply which helps to reduce cracking. It will also prevent the need to prime the ply first.
Are you putting underfloor heating into the screed at all?
you must all buy this song from any good download site for just 79p. Proceeds to Blesma, RAFA and RAFBF charities
Teresa Hind - The Fight Goes On
-
The Following User Says Thank You to Ajax123 For This Useful Post:
-
Re: Expansion joint / cold joint
Judging by the Pics Ajax, I think what he is planning on doing is screeding over the concrete area to bring it up to level with the insulation and ply and also the floor boards at the other end of the room, so he will be left with 3 different types of substrate
-
-
Re: Expansion joint / cold joint
oh no hang on... He's removed the floor boards, replaced with ply then injected the void with expanding foam. So maybe he's just planing on screeding the concrete area to bring up to level with the ply'd area?
-
The Following User Says Thank You to Colour Republic For This Useful Post:
-
Re: Expansion joint / cold joint

Originally Posted by
Colour Republic
oh no hang on... He's removed the floor boards, replaced with ply then injected the void with expanding foam. So maybe he's just planing on screeding the concrete area to bring up to level with the ply'd area?
Aaaah yes - you could well be right.
you must all buy this song from any good download site for just 79p. Proceeds to Blesma, RAFA and RAFBF charities
Teresa Hind - The Fight Goes On
-
-
TilersForums Contributor
Re: Expansion joint / cold joint
Correct, because of the extension i have to have 50mm screed as per building regs. Due to height of back door i have removed old floorboards and replaced with 18mm ply (the thickest i could use). These are nice and tight and the foam was just to stop anything falling down as there was a small gap with dwarf wall there.
This will hopefully be all one level. Its just how to get the two to sit next to each other so this can be tiled. The plan was to start the tiles along the join of the two, but if you think i can straddle the join, 50/50 either side that would make life easier.
Note: Ply is the maximum height this can go allowing for thin coat of adhesive and my thin tiles.
-
-
Re: Expansion joint / cold joint
Hi i always cut a bit of 6mm plyn to lenngth and place it between the new screed and new plywood and go back before its gone off properly take it out and your left with your expansion gap then silicone,cheers Mick
-
-
TilersForums Contributor
Re: Expansion joint / cold joint
Thanks, thats the advice i needed. Bet i haven't got any 6mm though!!!
Would you say its ok to bridge the join or should i lay the tiles either side?
-
-
Re: Expansion joint / cold joint
If you want to bridge the joint you will need ditra matting or durabace ci or g matting you could put the tiles either side but in doing that your governed with your setting out and you will have to put a 5 mm silicone joint there might not look to good, cheers Mick
-
-
TilersForums Contributor
Re: Expansion joint / cold joint
Thanks again, just went and got some fibres for the mix and checked friends garage for some 6mm ply. (none there).
I will probably get the screed down and then start another thread on the tiling aspect of it. Only thing though is i really am limited for height so won't be able to put down anything like ditra matting as i need to be low profile. Can't spare even a few mm.
Will post some pics and hopefully get some help on the best plan to get them down.
-
-
Re: Expansion joint / cold joint
I will leave the tilers on here to talk about the tiling aspect but from the point of vbiew of the screed you would be wise to either unbond the screed from the concrete using a poly membrane or make sure it is properly primed before you screed. The min depth you can use sand cement is 50mm. There is a potential issue of curling to take account of. To help minimise this you should cover your screed with a sheet of polythene for 7 days once installed in order to cure it. Then let it dry for 1mm per day before tiling. Prime the surface of the screed before placing any tiles on it.
You should not bridge the joint with tiles (even with uncoupling it could be a risk due to curling)
you must all buy this song from any good download site for just 79p. Proceeds to Blesma, RAFA and RAFBF charities
Teresa Hind - The Fight Goes On
-
The Following 2 Users Say Thank You to Ajax123 For This Useful Post:
CON5933 (05-11-2009), foxman (05-11-2009)
-
TilersForums Contributor
Re: Expansion joint / cold joint
The plan was that we are going for a dry mix with fibre. But we are going to prime it first and laying a cement slurry down for the bonding.
Once this is down, it will be a novelty not having a step in the middle of the room. I am happy to wait as long as it takes before tiling.
Some great advice, look forward to my next batch of pictures.
(hopefully might have found some decent software too, to aid in the design.)
-
-
Re: Expansion joint / cold joint
-
-
Re: Expansion joint / cold joint
I would let the screed dry first the way Ajax says but then you will be ok with a decoupling mat, it is what they are designed for alowing any moisture from new screeds to evaporate properly the way the mat is designed , looking at your photos your going to be pretty lucky if you put tiles either side of the two surfaces and for the setting out to be spot on especially as you have a sort of dog leg with your surfaces if you know what i mean. Mick
-
-
TilersForums Contributor
Re: Expansion joint / cold joint
I know i have the dog leg bit, so once screed is drying out i can start setting out on the ply to see what i have to play with and how it works out. The only slight advantage i have is the dogleg side will be where the kitchen units will sit.
-
The Following User Says Thank You to mercedism For This Useful Post:
Similar Threads
-
By jonty in forum Tiling Forum
Replies: 7
Last Post: 23-07-2010, 03:39 AM
-
By Dave in forum Tile Adhesive, Grout and Substrate Preparation
Replies: 9
Last Post: 18-02-2009, 09:14 PM
-
By jonty in forum Tiling Forum
Replies: 1
Last Post: 04-03-2008, 08:50 AM
Visitors found this page by searching for:
Tags for this Thread
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules
Tilers Forums is the UK's largest wall and floor
tiling forum. Advice is provided free of charge to all users. Tilers Forums does not take responsibility for any loss or damage caused due to following advice found on this forum. All wall and floor tiling should be carried out by a qualified wall and floor tiler. Views expressed on this forum are of the users and not
Tilers Forums. Views expressed on this tiling forum are of the contributor only and not the forum as a whole. Not all views should be taken as fact but simply the opinion of the person posting. Readers are reminded to seek professional advice before undertaking any wall and floor tiling project.
Tilers Forums is a Trading Style of Untold Developments Ltd.
Search Engine Optimisation, Web Development and Online Marketing for the UK.
Bookmarks