Welcome to Tilers Forums Tiling Forum


The UK's Biggest Tiling Forum for DIY and Professional Tilers; find


  •  » Tile Advice for Bathroom Tiles, Kitchen Tiles, Wall Tiles, Floor Tiles
  •  » Customers can Find a Tiler, or Wall and Floor Tilers can Find Customers
  •  » Tiling Tools, Tile Adhesive, Tile Grout and other Tile Products
  •  » Advice and Discussion related to Tiling Courses and Tiling NVQ's
  •  » Professional Tilers can find Business Advice, Discounts, Trade Accounts

DIY and Professional Wall and Floor Tilers are Welcome


Advice from by Tilers, Manufacturers, Distributors and Tile Suppliers


REGISTER HERE FOR FREE


p.s.: Registered members will not see this ad

Results 1 to 3 of 3
Discuss Levelling querie? in the Tile Adhesive, Grout and Substrate Preparation at TilersForums; Hi all...hope all well out there! Here's a question for you...looked at a floor job tonight. The tiles are onto a suspended floor screeded with 50mm concrete with water underfloor ...
          
  1. #1
    Tilers Forums Arms Member Perfect Tiling's Avatar
    Join Date
    Mar 2010
    Location
    Elgin, Moray.....North East Scotland
    Posts
    125
    Thanks
    29
    Thanked 32 Times in 21
    Posts

    Default Levelling querie?

    Hi all...hope all well out there!

    Here's a question for you...looked at a floor job tonight. The tiles are onto a suspended floor screeded with 50mm concrete with water underfloor heating. The floor has been down about 6 years and most of the tiles are loose. I'm assuming they are loose due to not a full bed of addy, the wrong addy, movement due to being a new build or the customer turning up the heat too soon! Retiling that part is easy enough. The main problem is that they are changing the room layout to make a new room with half the floor havinf a timber substrate and half having a heated screed. They not sure about tiling and may put down vinyl but want me to level the floor throughout that room. my thought was to remove tiles down to heated screed and remove floor boards and use ply to bring that half level to the screed, then possibly bond hardibacker or a marmox insulation board to go over screed and onto ply where it can be screwed. Obviously it cant be screwed onto the screed as I don't want to hit a water pipe. The floor size is only about 4sq mtr. Any thoughts....hope this makes sense!!

  2. #2
    tfs
    tfs is offline
    Tilers Forums Arms Member
    tfs's Avatar
    Join Date
    Nov 2007
    Location
    West Lothian
    Posts
    1,588
    Thanks
    290
    Thanked 456 Times in 332
    Posts

    Default Re: Levelling querie?

    no need to lift boards in my opinion. If the timber floor is solid just install you backer board over this then screed the conrete to the same height as timber floor/ backer board and once set screed over full floor. If the timber floor has deflection I would just add additional noggins mate to strenghten it. (if its in a poor state then replace.

    Will always be a chance of screed cracking at join unless you incorporate joint between both substrates.
    Last edited by tfs; 13-12-2010 at 08:51 PM.

  3. #3
    Tilers Forums Arms Member Perfect Tiling's Avatar
    Join Date
    Mar 2010
    Location
    Elgin, Moray.....North East Scotland
    Posts
    125
    Thanks
    29
    Thanked 32 Times in 21
    Posts

    Default Re: Levelling querie?

    Thanks mate...main reason I was going to lift the floorboards was because the customer wants the same height of floor throughout so won't accept a 6mm lip if I was to put the backerboard on top. Plan was to remove them (25 mm thick) then put down 18mm ply, 6mm hardibacker and skim with SLC. If he puts down vinyl then a crack will be hidden...tiling would require an expansion joint and he don't want that.

Similar Threads

  1. levelling
    By lcjohno in forum Tile Adhesive, Grout and Substrate Preparation
    Replies: 2
    Last Post: 10-04-2010, 11:36 AM
  2. levelling or not?
    By Aspect Tiling in forum Electric Underfloor Heating
    Replies: 20
    Last Post: 27-02-2010, 04:30 AM
  3. can i use apd before levelling
    By marke in forum Tile Adhesive, Grout and Substrate Preparation
    Replies: 3
    Last Post: 04-12-2009, 07:48 PM
  4. Self Levelling over ply
    By FreeD in forum Tiling Forum
    Replies: 3
    Last Post: 18-02-2009, 07:29 PM
  5. Self Levelling
    By theyomper in forum Tiling Tools
    Replies: 7
    Last Post: 12-11-2008, 06:19 PM

Visitors found this page by searching for:

Nobody landed on this page from a search engine, yet!

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Tilers Forums is the UK's largest wall and floor tiling forum. Advice is provided free of charge to all users. Tilers Forums does not take responsibility for any loss or damage caused due to following advice found on this forum. All wall and floor tiling should be carried out by a qualified wall and floor tiler. Views expressed on this forum are of the users and not Tilers Forums. Views expressed on this tiling forum are of the contributor only and not the forum as a whole. Not all views should be taken as fact but simply the opinion of the person posting. Readers are reminded to seek professional advice before undertaking any wall and floor tiling project.

Tilers Forums is a Trading Style of Untold Developments Ltd. Search Engine Optimisation, Web Development and Online Marketing for the UK.
DMCA.com
[Output: 63.46 Kb. compressed to 58.49 Kb. by saving 4.97 Kb. (7.83%)]

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28