Welcome to Tilers Forums Tiling Forum


The UK's Biggest Tiling Forum for DIY and Professional Tilers; find


  •  » Tile Advice for Bathroom Tiles, Kitchen Tiles, Wall Tiles, Floor Tiles
  •  » Customers can Find a Tiler, or Wall and Floor Tilers can Find Customers
  •  » Tiling Tools, Tile Adhesive, Tile Grout and other Tile Products
  •  » Advice and Discussion related to Tiling Courses and Tiling NVQ's
  •  » Professional Tilers can find Business Advice, Discounts, Trade Accounts

DIY and Professional Wall and Floor Tilers are Welcome


Advice from by Tilers, Manufacturers, Distributors and Tile Suppliers


REGISTER HERE FOR FREE


p.s.: Registered members will not see this ad

Results 1 to 5 of 5
Discuss Another question for Ajax. in the Tile Adhesive, Grout and Substrate Preparation at TilersForums; Sorry Alan but I could do with your advise, I am currently preparing a 170m2 floor. The floor is sand and cement fiber screed, over hot water ufh with kingspan ...
          
  1. #1
    TilersForums Trusted Member


    Phil Hobson's Avatar
    Join Date
    Aug 2009
    Location
    oldham
    Posts
    7,224
    Thanks
    5,128
    Thanked 3,115 Times in 1,925
    Posts

    Default Another question for Ajax.

    Sorry Alan but I could do with your advise, I am currently preparing a 170m2 floor. The floor is sand and cement fiber screed, over hot water ufh with kingspan underneath, when I priced the job I told the customer the heating system should be commissioned before tiling. My question is as the screed was not closed in very well I put a skim screed of Mapei latex plan trade, before over-laying a de-coupling membrane. The day joints also had opened up, so I thought the slc might knit the floor in cracked areas.


    I found out today that the floor has not been commissioned heat wise, just pressure tested. I would like your opinion as to if the floor could be heated up at this stage, before the tiling commences. Sorry to go on, but I was under the impression that the floor had been fired up before I started. Any imput would be very welcome

  2. #2
    Tilers Forums Pro - Screed Advisor
    Ajax123's Avatar
    Join Date
    Apr 2009
    Location
    Lincolnshire
    Posts
    3,014
    Thanks
    329
    Thanked 1,513 Times in 926
    Posts
    Blog Entries
    1

    Default Re: Another question for Ajax.

    I would say that it is essential that they commission and run the heating before you put the tiles down. There is some risk that heating the screed up will cause it to crack as these screeds do. It will also determine whether any delamination of the smoothing compound is likely.

    The SLC will not be capable of knitting hte cracked areas but as you have overlaid with an uncoupling membrane this gives you a fighting chance.

    My advice is do not do any further work untill the heating is comissioned. then see what happens. If you need further advice at that point then holler.

    Did you put anything in writing to cover your backside?
    you must all buy this song from any good download site for just 79p. Proceeds to Blesma, RAFA and RAFBF charities



    Teresa Hind - The Fight Goes On

  3. #3
    TilersForums Trusted Member


    Phil Hobson's Avatar
    Join Date
    Aug 2009
    Location
    oldham
    Posts
    7,224
    Thanks
    5,128
    Thanked 3,115 Times in 1,925
    Posts

    Default Re: Another question for Ajax.

    Thanks for that Alan, tiles wont arrive for another two weeks. Give them chance to fire it up, would you suggest bringing up the temp slowly as usual? the slc was two part with latex. Do you think this might help avoid any problems? Thanks again

  4. #4
    Tilers Forums Pro - Screed Advisor
    Ajax123's Avatar
    Join Date
    Apr 2009
    Location
    Lincolnshire
    Posts
    3,014
    Thanks
    329
    Thanked 1,513 Times in 926
    Posts
    Blog Entries
    1

    Default Re: Another question for Ajax.

    Start the heating up at 20 degrees and leave it for 3 days. lift the temperature by a MAXIMUM of 5 degrees per day aftet that up to its maximum operating temperature but don't exceed 55 degrees C flow temperature. leave here for 3 days and then reduce by the same 5 degrees per day back to ambient and then either tile it whilst it is at ambient (if the weather is particularly cold this is useful) or switch it off. If you take the switch it off option don't start tiling for around 2 or 3 days because the screed will need to contract fully. It is the hot bit in the middle and this final contraction that will usually show up issues with the leveller but I supect as it is cement on cement there won't be any issues.
    you must all buy this song from any good download site for just 79p. Proceeds to Blesma, RAFA and RAFBF charities



    Teresa Hind - The Fight Goes On

  5. The Following User Says Thank You to Ajax123 For This Useful Post:

    Phil Hobson (20-05-2010)

  6. #5
    TilersForums Trusted Member


    Phil Hobson's Avatar
    Join Date
    Aug 2009
    Location
    oldham
    Posts
    7,224
    Thanks
    5,128
    Thanked 3,115 Times in 1,925
    Posts

    Default Re: Another question for Ajax.

    Cheers Alan, as I said I was under the impression this had been done, before I started. You have put my mind at rest. Thanks

Similar Threads

  1. Replies: 1
    Last Post: 17-08-2008, 04:42 PM

Visitors found this page by searching for:

Nobody landed on this page from a search engine, yet!

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Tilers Forums is the UK's largest wall and floor tiling forum. Advice is provided free of charge to all users. Tilers Forums does not take responsibility for any loss or damage caused due to following advice found on this forum. All wall and floor tiling should be carried out by a qualified wall and floor tiler. Views expressed on this forum are of the users and not Tilers Forums. Views expressed on this tiling forum are of the contributor only and not the forum as a whole. Not all views should be taken as fact but simply the opinion of the person posting. Readers are reminded to seek professional advice before undertaking any wall and floor tiling project.

Tilers Forums is a Trading Style of Untold Developments Ltd. Search Engine Optimisation, Web Development and Online Marketing for the UK.
DMCA.com
[Output: 74.69 Kb. compressed to 68.44 Kb. by saving 6.25 Kb. (8.37%)]

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28