Discuss First Time Limestone Floor in the Canada area at TilersForums. The USA and UK Tiling Forum (Also now Aus, Canada, ROI, and more)

S

Stef

See - I don't get it with some of you folk - I have fixed thousands of metres of stone without decouplers, many times directly in a sand and cement bed.

All you have to do is make sure is that everything you do is compatible with your workflow.
& here's a limestone floor fixed to a screed without a decoupler, all be it a badly laid screed.
I have repaired this floor 3 times, they were told at install to decouple but I'm only a daft tiler, what do I know.

image.png image.png image.png image.png image.png image.png image.png
 
S

Spare Tool

C

Camper

The Anhydrate-Screed needs to be prepped properly!

1) Calcium-Carbide Moister measurement test. The moisture can't exceed 0.5% (with UFH 0.3%)
2) Laitence layer removed
3) Prime
4) Tiling can begin
5)Decoupling is not needed, to avoid cracking(longevity) movement joints need to be installed correctly!
 
B

Bill

& here's a limestone floor fixed to a screed without a decoupler, all be it a badly laid screed.
I have repaired this floor 3 times, they were told at install to decouple but I'm only a daft tiler, what do I know.
So this, in your own opinion, was a badly laid screed....so maybe that was the problem and not the actual fixing?
 
S

Stef

Tom go on the Schluter course you may be surprised as what you could learn there.
The guy that designed Ditra realised how tiling of old had lasted as long & that was to decouple it from the ground with a layer of sand.
 
C

Camper

If the screed was installed properly it already is decoupled (With styrofoam sheets instead of sand). With or without Ditra you still need to install movement joints. This is the reason for the cracks in the pictures above ( NO movement joints).

Floating-V6-LR1.jpg
 
B

Bill

Tom go on the Schluter course you may be surprised as what you could learn there.
The guy that designed Ditra realised how tiling of old had lasted as long & that was to decouple it from the ground with a layer of sand.
Not all did that. I have fixed onto suspended timber with sand and cement and had no problems....it is how you fix them that matters. I wish we had mobile phones 30 years ago that took photos!
 
B

Bill

Sorry I have no before or during photos but here is one I did not long ago...soft as turkish ceramics..... no decoupler fixed in sand and cement onto a concrete base......

20140603_143858.jpg 20140603_143753.jpg
 
S

Stef

If the screed was installed properly it already is decoupled (With styrofoam sheets instead of sand). With or without Ditra you still need to install movement joints. This is the reason for the cracks in the pictures above ( NO movement joints).

Floating-V6-LR1.jpg
"If the screed is installed properly"
If every screed was fitted this way then there would be no problem, that's where the decoupler comes into its own.
My pictures above are nothing to do with a movement join not being fitted.
No run is more than 3m long & is broken across the door ways, it was a badly fitted screed.
 

Reply to First Time Limestone Floor in the Canada area at TilersForums.com

Or checkout our tile courses and training forum or the Tile Blog / Latest Blog Posts

This website is hosted and managed by www.untoldmedia.co.uk. Creating content since 2001.
Tile Contractor Forum. The useful tile contractor website.

UK Tiling Forum Stats

Threads
67,334
Messages
881,097
Members
9,524
Latest member
andymtl24
Top