Originally Posted by Turkish View Post
As it sounds like the walls have been bonded and then skimmed then 4 weeks yes, if it was just a skim coat then maybe a couple of days would suffice but i would welcome any comments on that!

Turkish
Agree with you Turkish, If bonding the plasterer would have applied pva to the wall so very little suction into the brick or block wall and may take longer to dry.

"Experience is simply the name we give our mistakes"