I prefer to tile the whole floor then fit the units on top. Particularly when UFCH is used, the extra height could cause a problem with appliances if the units are fitted before tiling.

I also like to think that my lovely tiled floors will last longer than a few MDF boxes so it is easier to alter the kitchen layout if the whole floor is tiled.

That said, I don't mind either way, a lot depends on the client and kitchen fitter.