Order of work | | Hi all.
Just landed myself a couple of bathrooms and kitchen to be retiled. In both bathrooms the old suites and tiles are going to be ripped out and replaced floor and wall. Kitchen units and floor coverings also ripped out and replaced.
I take it its best to tile the whole floor before the new bathroom suite is installed?
And to work along side the plumber when tiling the walls?
And for the kitchen its best for the units to all be installed before the floor and splashback is tiled?
Thanks
Aaron |